Road 3B, Corridor 2, New Providence – Environmental Management Plan and environmental oversight as per EMP requirements

The project involved development of an Environmental Management Plan (EMP) for the road construction; EMP included overview of environmental impacts, mitigation methodologies to be utilized, training materials for construction staff, design of organizational structure for EMP implementation, development of environmental method statements and monitoring schedule. Tasks also involved weekly monitoring for environmental impacts based on EMP requirements. SEV was the project lead and responsible for coordinating all fieldwork as well as completing some of the assessment and monitoring fieldwork, liaising with Government agencies and ensuring deliverables were made in a timely manner, including monitoring reports.